construction process
|
25 April -2024 |
Monolith works
At the +18.98 mark in Bagebi, the work on the monolith of the residential floor has been completed and the columns of the 8th floor are being reinforced (rebar burning). |
Gallery
|
Gallery |
|
|
|
03 April -2024 |
6th floor
Columns and rails have been poured on the 5th floor, while iron work is being done on the 6th floor. |
Gallery
|
Gallery |
|
|
|
08 March -2024 |
5th floor
At the +12.58 mark, preparatory works for the columns of the 5th floor are in progress. |
Gallery
|
Gallery |
|
|
|
23 February -2024 |
Columns
From the first to the 5th floor, the monolith work was completed, and the support columns were arranged on the 6th floor. |
Gallery
|
Gallery |
|
|
|
09 February -2024 |
Construction of convoys
In Bagebi, the columns of the 2nd residential floor are being pulled out at +6.18 mark. |
Gallery
|
Gallery |
|
|
|
26 January -2024 |
2nd residential floor
The construction of the 2nd residential floor at +6.18 mark has started in Bagebi. |
Gallery
|
Gallery |
|
|
|
09 January -2024 |
3rd floor
The removal of the 3rd floor has been completed (+2.98 marks). |
Gallery
|
Gallery |
|
|
|
20 December -2023 |
Column
Preparatory works for the columns of the 3rd floor are in progress. |
Gallery
|
Gallery |
|
|
|
24 July -2023 |
Land works
Land cutting works are in progress. |
Gallery
|
Gallery |
|